The Making of the TPT (Malcolm Parker)

Anyone travelling in the corridor between the Mersey and Humberside through Merseyside, Cheshire, Derbyshire, East, West and South Yorkshire will not have to go far before coming across a blue finger post or some other direction sign pointing to the Trans Pennine Trail as it makes its way from Southport to Hornsea.

It’s a route that has now become firmly established in the landscape and provides a regular source of pleasure for walkers, wheelers, cyclists, joggers and horse riders. But how did the TPT come into existence?

The story begins in the Countryside Section of the Planning Department in Barnsley Metropolitan Borough Council. This was formed when South Yorkshire County Council was abolished in 1986 and I was appointed to head the section.

Among the responsibilities that came our way was managing the public rights of way and, as a countryside unit charged with encouraging more residents to appreciate and use the many attractive rural areas of Barnsley, we were keen to exploit any additional opportunities to increase access.

It’s probably true to say that Barnsley is still more famous as a former coal mining area than as a rural idyll. By the mid 1980’s the coal industry was in terminal decline and in its wake there was a legacy of dereliction leaving areas of land with the potential for restoration and reuse.

The collieries had been served by a complex network of railways most of which had no passenger traffic. Therefore they fell into disuse along with the pits which were their raison d’etre. Perhaps they might be turned into an asset and reused for recreation similar to the longer cycle ways in the Peak District such as the Tissington and High Peak Trails?

Our first step was to undertake a survey to assess the disused lines’ potential. We were aware of an organisation called Sustrans which had been pioneering the conversion of disused railways to cycle ways and John Grimshaw was invited to Barnsley to tell us more about his ideas and to seek his advice.

John talked enthusiastically about the recently completed Bath-Bristol scheme which was proving very popular. The upshot was that Sustrans was commissioned to carry out the full survey. I should also mention the support provided by the Countryside Commission (now part of Natural England) whose Leeds office provided much encouragement and, even more importantly, considerable aid to fund the study.

The Sustrans report identified a number of lines which they believed would provide excellent opportunities for conversion but the cherry on the cake was the 32km long line from Wombwell which snaked its way westward across the full length of the borough until it plunged under the Pennines through the Woodhead tunnel.

The line had closed in 1981 when the flow of coal from Barnsley to the power station at Fiddlers Ferry ended. Although it had been electrified and boasted a relatively modern tunnel under the spine of England it succumbed to the cuts.

The Council fought valiantly for its retention and at the very least wanted to keep the routeway intact with an eye to any future development. We thought we could keep its integrity whilst making some immediate use of the track-bed. The Wombwell – Dunford route was absolutely key to the creation of the TPT but we were still a long way from the east and west coasts!

In the 1980’s Barnsley was not alone in trying to develop new recreation facilities and Sustrans was aware of schemes on the Liverpool Loop Line and the disused railway between Selby and York. Why not try to link our efforts to those of neighbouring authorities and see if we could in fact get from coast to coast? It’s fair to say that the idea was greeted with some scepticism in the office! We had a fair idea of where the route might go and undeterred, I got out the Ordnance Survey maps and the Municipal Year Book with details of all the local authority areas.

When I announced that it would involve over twenty councils the office sceptics had a field day. ‘You’ll never get so many local authorities to co-operate on any project’ was the common refrain. However, early in 1989 a letter was sent out to all the councils inviting them to a meeting in Barnsley to discuss the idea. The response was all we could have hoped for. It seems we were all interested in developing new routes and all were agreed how much better it would be if the work in our areas could carry on beyond our authority’s boundary.

We were trying to create a long chain of end to end routes and it would fail if any link was missing. We left the meeting thinking that we could indeed build our coast to coast chain. It was also at this early stage that the multi user nature of the TPT was established. We wanted to create a route for cyclists, horse riders and walkers. This might mean that some sections needed local diversions but we tried hard to accommodate all users wherever possible. We were also keen to emphasise the fact that although the route might not pass through high quality landscapes, as was then the case with most long distance routes in the UK, it had the enormous benefit that it ran through or close to many towns and cities with over a quarter of the UK population living within twenty miles of the route.

Hopefully we could develop a facility which some would wish to complete from coast to coast but our main aim was to serve our local communities – a safe place for families to ride bikes in a traffic-free environment or for walkers to stroll from their homes into the urban fringe and beyond.

The next absolute essential was to secure the full political backing of the local authorities. And here both we in Barnsley and the wider TPT community had the great good fortune that Councillor Robin Norbury began his long association with the project. Robin was Chairman of Barnsley Planning Committee and his unstinting efforts in support of the TPT became the bedrock on which so much was based. He began by supporting our ideas for the route in Barnsley but soon moved on with us to champion the grander scheme. He went on to serve as Chair of the TPTR Members Steering Group and Executive for many years, continuing long beyond his retirement from local politics which speaks volumes about his commitment.

Having lit the flame and got a positive initial response, the major challenge now was the day-to-day organisation of a rather unwieldy scheme. The officers had the task of delivering it on the ground but how did you service over twenty local authorities, all moving at variable speeds as they developed the route? How could we ensure that the benefits of the scheme as a whole were realised?

At this point the scheme was being run from my desk and the TPT was not my only responsibility. It was obvious that this arrangement would not deliver the project in the long term and a dedicated full time officer was essential. It would be quite expensive but as the officer would be supporting twenty or so authorities, what about the idea of them all sharing the cost? Another good day for the office sceptics!

Support is one thing, but financial commitment is quite different. However, thanks again in no small part to the help of a Countryside Commission grant, we could afford an officer and associated support costs if each of the partner authorities contributed about £1000 a year. That sounded a far easier proposition to sell to any doubters. Another letter was dispatched to the authorities, another successful meeting ensued and over the next few weeks cheques arrived in Barnsley from across the country as each partner gave its financial backing.

Thanks to Robin’s influence, Barnsley Council provided office space which explains why the TPT is still run from there to this day. And so to the interviews – and our next piece of great good fortune. If Robin provided the political support for the Trail, Pam Ashton, who was appointed as the first TPT officer was the person with the driving force to realise the project. It is perhaps no co-incidence that, like Robin, Pam’s involvement has continued beyond her professional involvement and continues today as Deputy Chair for the Friends of the TPT.

So now we were up and running – but with a long way still to go. Pam was working with over twenty authorities from her home on Merseyside and her office in Barnsley and it soon became clear that even one full time officer wouldn’t be enough. At that point as I recall, the TPT’s current Lead Officer, Mandy was seconded from my Countryside Section to provide help.

Pam travelled hundreds of miles building a network of officers responsible for the TPT in each authority and devised the regional groups so that neighbouring authorities could meet more frequently to co-ordinate their work and I see from the newsletters that these groups still exist.  Pam worked tirelessly on every aspect of the TPT from the printing of route maps, signposting, advertising, talking to cycling and horse riding organisations and printing t-shirts and even organising a competition from which the TPT logo was selected.

It was a hectic few years for her but the results are clear for all to see. In addition to the regular officer meetings to discuss progress, the elected members kept abreast with developments at annual meetings. There was never a shortage of authorities wanting to host the meeting and wherever possible we linked the gatherings to the opening of a new section of the route. Memories come back of mayoral limousines parked by the side of remote sections of disused railway as ribbons were cut and the ‘chain gang’ posed for the obligatory photograph.

During the first few years we got as far west as Liverpool and as far east as Hull, the latter being a particularly memorable meeting as it was held on board the then North Sea Ferry ‘Norland’. This venue was linked to the proposal to incorporate the TPT into the European Long Distance footpath route and it did indeed become the UK section of E8, the route from Istanbul to Ireland.

This year is the 35th year since the idea of a coast to coast Trans Pennine Trail was launched but thanks to the efforts of countless officers who designed the route, applied for the grants and oversaw its development, the improbable idea did indeed come to fruition.

Today it is firmly established as a valued asset for everyone from local users to charity fund-raisers using it to link east and west coasts. And for me personally it has provided an excellent retirement facility and I regularly get my bike out to ride the section form my home in Penistone up to Dunford Bridge (but check the wind direction before you go – it can be fifty minutes heading west and twenty five coming east with both the wind and a favourable gradient!).

Malcolm Parker, Friends of the Trans Pennine Trail
Date: 26th July 2024

Listen to Malcolm’s Making of the TPT podcast on the TPT podcast channel at: https://shows.acast.com/trans-pennine-trail-national-office/episodes/.

 

Interactive Map

See our interactive mapping for detailed route alignment and route diversions.

Distances

Using the tables below you can work out how far you want to go on the TPT.

Useful Links for Information

Check our useful links regarding accessibility

Share This